Friday 9 April 2010

Building progress


Its week 3 and work is progressing on site nicely at present on this extension.  We did run into a few small problems in that the depth of the excavation of the foundations was deeper than expected. As everything has to be manually moved, it was decided to put a suspended concrete floor in with Conc T-beams rather than taking out all the fill under the floor.

At this tage the block work of this element of the project is complete, with the roofers scheduled to start on Monday.  Next week will see the builders remove the existing garage roof and commence on the first floor extension. It is expected that the majority of the work will be complete within the next 5 weeks.